Title
Testing a Bridge Rectifier
URL Name
Testing-a-Bridge-Rectifier
Summary
Provides the procedure to test the bridge rectifier using a diode test to determine if the component is good or requires replacement.
Owner
Mike Sotelo

Question

How do I test the bridge rectifier?

What tool is required to perform a diode test on the bridge rectifier?

Why must the system be fully de-energized and locked out before testing?

Which wires should I disconnect for the bridge rectifier diode test?

Why disconnect only the DC output wires and not the AC input side?

How do I identify the positive (+) and negative (–) terminals on the rectifier?

What is the correct multimeter lead placement for the diode test?

What multimeter setting is required for the bridge rectifier test?

What meter reading indicates a good bridge rectifier?

What meter reading indicates a bad bridge rectifier that needs replacement?

Why mark or note wire positions before disconnecting?

What should I do if the bridge rectifier test shows ~0.40V–0.60VDC?

Is lockout/tagout required before touching the bridge rectifier?

When is the bridge rectifier test applicable in airfield lighting systems?

Content

Tools Required


RMS Multimeter with Diode Test Mode.

Step 1: Power Down and Lockout


Ensure the system is fully de-energized:
- Turn off the CCR (or disconnect mains power if PSUV system)
- Engage lockout/tagout before touching any internal circuitry

Step 2: Identify and Disconnect Wires


Locate the bridge rectifier
Identify the red and black wires connected to the rectifier’s output terminals.
Mark or note wire positions before disconnecting.
Disconnect only the output wires (DC side), not the AC input side.
Note: The positive (+) terminal is usually rotated 90° from the others and is connected to the red wire. The black wire connects to the negative (–) terminal, diagonally placed from the positive.

Step 3: Perform Diode Test


Set your multimeter to Diode Test Mode.
Place the black (–) multimeter lead on the positive (+) terminal.
Place the red (+) multimeter lead on the negative (–) terminal (opposite corner).

Step 4: Evaluate Results


Meter Reading | Condition
~0.90V–1.00VDC | ✅ Bridge Rectifier is Good
~0.40V–0.60VDC | ❌ Bridge Rectifier is Bad – Replace It

Safety Reminder


Always maintain safe working conditions by using appropriate personal protective equipment (PPE) where necessary.
Only qualified service personnel should perform bridge rectifier testing on airfield lighting systems.
Follow lock out / tag out procedures and verify absence of hazardous voltage before handling internal circuitry or junction box components.

Airport Lighting Company | Troubleshooting Instruction

Internal Notes

Digital Engagement Response

Article Created Date
2/20/2026, 5:17 PM
Publication Status
Published
Created Date
2/20/2026, 5:17 PM
Article Total View Count
2,011
Created By
Mike Sotelo, 2/20/2026, 5:17 PM
Archived Date
Last Modified Date
2/20/2026, 5:17 PM
Last Modified By
Mike Sotelo, 2/20/2026, 5:17 PM
Last Published Date
2/20/2026, 5:17 PM

Assigned To
Assigned By
Assignment Due Date
Assignment Date
Assignment Note
Troubleshooting Test

Related Articles

  • Performing Megger Testing for Airfield Lighting Systems
    Number of Views345
  • Testing a GDT
    Number of Views23
  • Testing an LVCV2 Power Supply
    Number of Views65
  • Perform a Diode Test on the L861 LED Light Engine
    Number of Views115
  • L-828, Type L-829 Ferroresonant Constant Current Regulator (CCR) - Running a Manual Megger (IRMS) Test
    Number of Views72

Trending Articles

  • Performing Megger Testing for Airfield Lighting Systems
  • L-880(L)/L-881(L) Precision Approach Path Indicator (PAPI) - Overview and Application
  • L-849-V-A/E / L-849-I-A/E Unidirectional Runway Approach Lights - Set Up Procedure for a 3 Step CCR
  • L-849-V-A/E / L-849-I-A/E Runway End Identifcation Lights (REIL) - Overview and Application
  • L-862(L), L-862E(L) High Intensity LED Runway Light - Installation Instructions
Powered by Salesforce Logo
Loading
Testing a Bridge Rectifier